# Attracting data center load before defining how to interconnect it

> Seven days apart, Chile's government convened the global data center industry and published a plan that projects that demand and reinforces the need to expand transmission. Both are public record. What has not yet been defined is a regulatory framework specific to this type of load.

- Published by: EnergySage, an energy intelligence firm (Santiago, Chile)
- Date: 2026-08-18
- Revised: 2026-11-12
- URL: https://energysage.cl/en/analisis/data-centers-demanda-convocada-transmision/
- Spanish version: https://energysage.cl/analisis/data-centers-demanda-convocada-transmision/

On July 31, 2026, Chile's Ministries of Energy and Science convened the first public-private meeting of the Chile Energy Data Hub, bringing together more than 60 executives and officials from power generators, global technology companies, and public agencies to discuss electricity supply for data centers.

A week earlier, on July 24, the Ministry of Energy published the preliminary report of the Long-Term Energy Planning (PELP) 2028-2032, which is open for public comment until August 24, 2026. For the first time, the document treats "Data Centers" as a demand subsector in its own right: it estimates 198 MW of installed data center capacity nationwide in 2024, on a trajectory reaching about 594 MW by 2030, and in one of its scenarios adds, for the Antofagasta Region, "an installed capacity of 500 MW by 2030, rising to 1 GW by 2057."

On the grid, the same report "reinforces the need to expand transmission along the Charrúa-Ancoa-Alto Jahuel-Lo Aguirre corridor at 500 kV by at least 1,750 MVA" — to carry wind power toward central and northern Chile — and identifies 220 kV expansions "with lines that would need up to six times their current capacity, across all scenarios" — concentrated in the Antofagasta and Maule regions.

Both are public, official actions, taken seven days apart.

## Two timelines that do not line up

Attracting load and building the infrastructure to serve it run on different clocks. An international roadshow can generate interest within months. A bulk transmission expansion is measured in years, and its delivery depends on planning, tendering, and construction processes that are already defined and underway.

That asymmetry is not unique to Chile, nor does it indicate a lack of coordination: it is inherent to both processes. What distinguishes jurisdictions is how they manage that gap while it lasts.

## Australia has already set out a framework

In August 2026, the Australian Energy Market Commission (AEMC), which writes the rules for Australia's electricity market, published the advice it had delivered to energy ministers, setting out a four-point framework for large loads. It is not yet binding: implementation rests with governments. Under it, large loads would:

- Back their consumption with newly built renewable generation rather than existing capacity.
- Contract for firming capacity.
- Register as market participants, with the obligations that status carries.
- Provide demand-side flexibility to the system.

The Australian Energy Market Operator (AEMO), which operates the grid, projects that this load will reach almost 10% of total electricity demand in the National Electricity Market (NEM), Australia's main grid, by 2050. Given that projection, the AEMC recommends treating large loads as market participants with obligations before they arrive at scale.

The difference between the two approaches is not about a country's appeal or the quality of its resources. It is about when the rules are set: before the load materializes, or after.

## What remains undefined

In Chile, a data center interconnecting today does so under the general rules that apply to any customer of its size. No regime recognizes its particular characteristics (intensive consumption, high load factor, acute sensitivity to interruption, and in some cases the ability to shift load over time) or translates them into obligations or differentiated interconnection terms.

That gap cuts both ways. For the system, it means fast-growing load is added without specific instruments to manage its impact. For the investor, it means the conditions under which a project was evaluated may change once the framework is defined.

The PELP comment period closes on August 24, 2026. That is where this discussion formally takes place, and where the demand projections validated now will shape the next decade's expansion decisions.

<aside class="analisis__actualizacion" id="actualizacion" aria-label="Update">

**Update, November 12, 2026**

Three developments add to this analysis; the first two are from November 2026.

- **The planned grid.** On November 10, the CEN, Chile's independent system operator (ISO), published the award record for 17 new transmission projects. Under the decrees that defined them, the projects have between 48 and 72 months to enter service, counted from the publication of the award decree, which has not yet been issued.
- **The demand.** On November 11, Amazon Web Services (AWS) began operating its infrastructure region in Chile, with three data centers in the Santiago Metropolitan Region.
- **The exception route.** Article 102 of Chile's General Electricity Services Law (LGSE) allows Chile's National Energy Commission (CNE) to authorize transmission projects outside the planning process, based on a written justification approved by the system operator. Since 2021, the CNE has used this route to authorize at least four transmission projects to serve data centers: one in Colina, one in Pudahuel, and two in Quilicura. In the most recent case, the system operator stated that under regular planning the project would have entered service in 2032; the resolution sets in-service deadlines of 27 and 39 months for its two works.

Sources: CEN, Chile's independent system operator (ISO), award record (November 10, 2026); Ministry of Energy Exempt Decrees No. 354/2025 and No. 13/2025; CNE Exempt Resolutions No. 396/2021, No. 171/2024, No. 190/2025, and No. 550/2025; Revista Electricidad and La Tercera (November 11, 2026).

</aside>
